Project Overview

Facility Specifications

  • • 850,000 sq ft total facility area
  • • 45-foot clear height throughout
  • • 4 distinct temperature zones (-20°F to 65°F)
  • • 50,000 pallet positions
  • • Automated storage and retrieval system

Project Leadership

Sarah Johnson
Sarah Johnson, PE
Project Manager
Michael Chen
Michael Chen, SE
Lead Engineer
  • • Safety Director: Robert Martinez
  • • 150+ skilled craftspeople
  • • 24/7 project supervision

Achievements

  • • Completed 2 weeks ahead of schedule
  • • Zero lost-time incidents
  • • LEED Gold certification achieved
  • • 25% energy efficiency improvement
  • • Client satisfaction score: 98%

Project Location

Project Location Map
Fremont, CA
37.5485° N, 121.9886° W

Strategic Location Benefits

  • Direct access to I-880 and I-680 corridors
  • 15 minutes from Oakland International Airport
  • Central Bay Area distribution hub
  • Serves 8 million+ customers within 100 miles

Project Timeline

Project Schedule
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
Design & Permitting
100% Complete
Site Preparation & Foundation
100% Complete
Structural Steel & Envelope
100% Complete
MEP & Automation Systems
100% Complete
Final Commissioning
100% Complete
1

Design & Permitting

Months 1-4

Comprehensive site analysis, architectural design, and regulatory approval process including environmental impact assessments and local permitting.

2

Site Preparation & Foundation

Months 5-8

Excavation, utility installation, and concrete foundation work including specialized footings for heavy refrigeration equipment and automated systems.

3

Structural Steel & Envelope

Months 9-14

Steel frame erection, insulated panel installation, and roofing systems with specialized thermal barriers for temperature-controlled environments.

4

MEP & Automation Systems

Months 15-17

Installation of refrigeration systems, electrical infrastructure, and automated storage equipment with comprehensive testing and commissioning.

Final Commissioning & Handover

Month 18

System validation, performance testing, staff training, and facility handover with comprehensive documentation and warranty coverage.

Project Resources

Download Project Brief

Get detailed insights into the Costco Distribution Center project including specifications, timeline, and key achievements. Enter your email to receive the comprehensive project brief.

Costco Distribution Center Project Brief PDF Cover

Costco Distribution Center Project Brief

Comprehensive 24-page project overview including design specifications, construction timeline, and performance metrics from this award-winning cold storage facility.

850,000 sq ft facility specifications
Multi-zone temperature control systems
Automated storage and retrieval details
Safety performance and achievements
LEED Gold certification process
Construction timeline and milestones
Free Download

Get Your Copy

Enter your email address to receive the project brief instantly.

By downloading, you agree to receive occasional updates about similar projects. Unsubscribe anytime.

Client Testimonials

"Span Construction delivered an exceptional facility that exceeded our expectations. Their attention to detail in the temperature control systems and automation integration was outstanding. The project was completed ahead of schedule with zero safety incidents."
Costco Logo
Tom Walker
Senior Director of Construction
Costco Wholesale
"The level of coordination and communication throughout this complex project was remarkable. Span's team worked seamlessly with our operations to ensure minimal disruption to our existing facilities while delivering a world-class distribution center."
Jennifer Martinez
VP of Supply Chain Operations
Costco Wholesale

Ready to Start Your Project?